21627 |
APPLICATION FINALISED |
PERMISSION |
C |
22/07/2021 Thursday |
Gromane Limited |
Killeen Co. Kilkenny |
for a ten-year appropriate period planning permission for development of this site; the proposed development will constitute the provision of the following: The installation of 31.49km of a 38kV underground electrical cabling and all other ancillary works including joint bays, culverts, maker posts and all associated development in the townlands of Killeen, Rathmacan, Gortnagap, Kyleballyoughter, Courtstown, Raheen, Lates, Curraghscarteen, Canvarstown, Trenchardstown, Lisnalea, Hillend, Coldharbour, Killahy, Greenhill, Lughinny, Craddockstown, Tubbrid Lower, Clomantagh Lower, Barna, Newtown, Kilrush, Belville, Lodge, Garranamanagh, Balleen Lower, Lodge, Tifeaghna (Browne), Lodge Demesne West, Lodge Demesne East, Clontubbrid, Clone, Acragar, Skinstown, Lisdowney, Seskin South, Parksgrove Ballyragget & Moatpark, Co. Kilkenny. Advisory Note: The full extent of the grid connection is 33.8km, and a separate planning application will be made for an underground grid connection to Tipperary County Council. The development comprises part of an overall development for which planning permission was granted for a 9 turbine wind farm and all associated works on lands located in the townlands of Farranroy Upper, Farranroy Lower, Coolnashinnagh & Gortnasmuttaun, Co. Tipperary. The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement. |
2360330 |
APPLICATION FINALISED |
PERMISSION |
C |
21/07/2023 Friday |
John Kennedy and Niall Drennan |
Ballyconra, Parksgrove and Moatpark Ballyragget Co. Kilkenny |
for the Proposed installation of a network connection and grid connection, and minor amendments to solar farms previously approved under planning application references 17/669 and 22/126. The proposed development will consist of the installation of a 33kV network connection between the solar farms approved under planning application references 17/669 and 22/126 comprising: c. 921m of overhead line and 9 No. wooden poles; onward connection of said approved solar farms to Ballyragget 38kV Substation by installation of a 38kV cable comprising c. 786m of underground cable and c. 395m of overhead line on 5 No. wooden poles; amendments to solar farm approved under planning reference 17/669 comprising removal of substation and replacement with solar panels; amendments to the layout of the substation approved under planning reference 22/126, and all associated site works |
98390 |
APPLICATION FINALISED |
PERMISSION |
C |
15/04/1998 Wednesday |
Electricity Supply Board |
to the rear of ESB's existing 38kV transformer stat. Moatpark,Ballyraget |
erect 110 kV outdoor transformer station to include 3 end masts, transformers & assoc. 110kV & 38kV structures & equipment, control building, septic tank, percolation area, connecting internal roadway & revised recessed entrance off public road. |