Planning application details ref: 2360443 Kilkenny County Council

100%100% Complete (warning)

Planning Application: 2360443 (Kilkenny County Council)
File Number: 2360443
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 05/10/2023 Decision Due Date: 29/11/2023
Validated Date: 05/10/2023 Invalidated Date:
Further Info Requested: Further Info Received:
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 27/11/2023
Leave to Appeal: Appeal Date: 14/12/2023
Commenced Date: Submissions By: 08/11/2023

Applicant Details

Applicant name: ESB The Electricity Supply Board
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: The proposed development will consist of the completion of the partially constructed 38 kV OHL which forms part of the Kilkenny loop connection. The proposed development involves the construction of the 12 remaining poles (poles 12-23) and stringing with overhead lines, over a distance of approximately 2km, and all associated works including temporary works required. These works will complete the loop project which was previously granted permission in September 2005 (Ref. P.05/452)
Development Address: Passes through the townlands of Cellarstown East, Higginstown, Eagleshill, Cellarstown West and Cellarstown Upper, Kilkenny, County Kilkenny., County Kilkenny, Kilkenny 5000 sheets 4707, Kilkenny 2500 sheets 4706-B,4768-C,4705-D,4706-D, 4767-A,4768-D,4705-B,4767-B,4706-A,4767-D,4706-C Kilkenny 1000 sheets 4766-15,4766-10,4766-05,4766-25,4766-20, 4767-11,4705-25
Architect Name: Location Key: CELLARSTOWN, CO KILKENNY
Electoral Division: Planner: Ross O'Shea
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 27/11/2023 Manager Order: 683
Decision Type: Conditional Number of Conditions: 8
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 11/11/2029
Decision Description: The proposed development will consist of the completion of the partially constructed 38 kV OHL which forms part of the Kilkenny loop connection. The proposed development involves the construction of the 12 remaining poles (poles 12-23) and stringing with overhead lines, over a distance of approximately 2km, and all associated works including temporary works required. These works will complete the loop project which was previously granted permission in September 2005 (Ref. P.05/452)

Appeal Details


Appeal Details
Notification Date: 18/12/2023 BP Reference #: ABP-318699-23
Appeal Type: THIRD PARTY File Forward Date:
Submission Due Date: 23/01/2024 Submission Sent Date:
Appeal Decision: MODIFIED Decision Date: 12/11/2024
Withdrawn Date: Dismissed Date:
Reason: